Design-Build Archives - PC Construction /news/tag/design-build/ Building Stronger, Together Thu, 21 Aug 2025 18:16:29 +0000 en-US hourly 1 https://wordpress.org/?v=6.8.1 /app/uploads/2022/06/cropped-Site-Icon_02-32x32.jpg Design-Build Archives - PC Construction /news/tag/design-build/ 32 32 Collaborative Milestone Marks Successful Completion of Innovative Bioenergy Facility /news/collaborative-milestone-marks-successful-completion-of-innovative-bioenergy-facility/ Thu, 21 Aug 2025 18:16:29 +0000 /?p=13043 The PC Construction team has achieved a critical milestone on the Bioenergy Facility project at WSSC Water鈥檚 Piscataway WRRF 鈥?the completion of the first annual maintenance of the Cambi B6-4 Thermal Hydrolysis Process (THP) and switchover to the redundant module. The Cambi THP is a major component of the $270 million Bioenergy Facility and […]

The post Collaborative Milestone Marks Successful Completion of Innovative Bioenergy Facility appeared first on PC Construction.

]]>
WSSC Water Piscataway WRRF Bioenergy FacilityThe PC Construction team has achieved a critical milestone on the Bioenergy Facility project at WSSC Water鈥檚 Piscataway WRRF 鈥?the completion of the first annual maintenance of the Cambi B6-4 Thermal Hydrolysis Process (THP) and switchover to the redundant module.

The Cambi THP is a major component of the $270 million Bioenergy Facility and serves as聽a pre-treatment process upstream of anaerobic digestion, utilizing high temperature and pressure (375掳F at 170 psi) to break down organic matter in the municipal wastewater sludge.聽This process enhances the biodegradability of the material, leading to increased biogas production and improved dewatering of the resulting Class A biosolids, all while reducing the volume of residual solids requiring offsite disposal.聽This particular facility is unique in that it is the first THP facility in the world to incorporate Cambi鈥檚 鈥榬edundant modules鈥? providing WSSC Water a full backup system in case a singular unit experiences failure.

The new Bioenergy Facility has been in operation for just over a year with operation and preventative maintenance tasks performed by WSSC Water. To ensure optimum performance and long-term reliability, Cambi requires the unit be taken out of service annually for maintenance, requiring a full shutdown. During that time, piping is taken apart and manways to the vessels are opened to properly clean and remove solids deposition. Pressure relief valves and the seats on the sludge and steam valves are also replaced.

Prior to the shutdown, the facility was processing over 65 dry tons of biosolids each day. Extensive coordination and pre-planning were required with WSSC Water operations staff located at the main Piscataway WRRF facility as well as the four other WSSC Water treatment plants that truck biosolids to the site. A shutdown and maintenance plan along with a detailed hour-by-hour schedule for the planned seven-day shutdown was developed, outlining individual work tasks and identifying which member of the integrated team was responsible for each task. PC Safety Specialist Mark Becker was also instrumental in working with Cambi and WSSC Water during this stage of the operation to address the work exposures of stored energy, high steam pressure and high temperatures. After multiple pre-planning sessions, the final plan review was held two days before shutdown initiation.

This was an intensive, collaborative effort involving all team members. The primary operation was led by Cambi with PC Construction providing administrative, safety and mechanical support and WSSC Water stepping in with operational oversight and additional mechanical support. In addition, Jet Blast provided high pressure washing and vacuum trucking services for the cleaning and flushing of the piping and vessels.

Special thank you to PC Construction鈥檚 awesome 鈥淭ear Down, Bolt-up, and Turn & Burn Team鈥?whose expertise and talents contributed significantly to this successful outcome: Emanuel 鈥淢occo鈥?Negron, Alejandro 鈥淵oyo鈥?Vargas, Luis 鈥淐atracho鈥?Rivera, Luis Rivas, Betzaida 鈥淏ee鈥?Reyes and Gilberto 鈥淪horty鈥?Reyes. Cambi鈥檚 Dawn Taylor said it best: 鈥淚 genuinely enjoyed working onsite with Mark, Mocco, and his crew. Their professionalism and teamwork truly stood out. Mocco and his team put in long, demanding days to accomplish a significant amount of work, all while maintaining a positive attitude and strong dedication.鈥?/p>

Following the safe and successful completion of maintenance, the THP was returned to service utilizing the redundant system one day ahead of schedule, a testament to the extensive planning and incredible team effort every member brought to the table. This milestone not only marks a successful first-year maintenance cycle but also reinforces the strength of collaboration, planning and technical excellence that has defined the entire Bioenergy Facility project.

WSSC Water Piscataway WRRF Bioenergy Facility WSSC Water Piscataway WRRF Bioenergy Facility WSSC Water Piscataway WRRF Bioenergy Facility WSSC Water Piscataway WRRF Bioenergy Facility Schedule

A snapshot of the first two days of shutdown maintenance work, scheduled by the hour.

The post Collaborative Milestone Marks Successful Completion of Innovative Bioenergy Facility appeared first on PC Construction.

]]>
Join PC Construction at the DBIA Water/Wastewater Conference /news/join-pc-construction-at-the-dbia-water-wastewater-conference/ Thu, 13 Mar 2025 14:29:44 +0000 /?p=12524 The DBIA Water/Wastewater Conference is just around the corner, held this year at National Harbor, Maryland. This industry-leading conference brings together owners, engineers, contractors and practitioners in one educational environment to learn, promote and share design-build experiences in the water and wastewater industry. PC Construction has been at the forefront of construction, design and project […]

The post Join PC Construction at the DBIA Water/Wastewater Conference appeared first on PC Construction.

]]>
The DBIA Water/Wastewater Conference is just around the corner, held this year at National Harbor, Maryland. This industry-leading conference brings together owners, engineers, contractors and practitioners in one educational environment to learn, promote and share design-build experiences in the water and wastewater industry.

PC Construction has been at the forefront of construction, design and project delivery in the water and wastewater market for over 60 years. From our first collaborative delivery project 45 years ago to the largest design-build water infrastructure projects of today, our teams and our work represent the largest East Coast water/wastewater geographical footprint in the market.

In our current portfolio, we are incorporating groundbreaking new technology at active plants in many communities. From biosolids transformations to advanced water treatment systems, PC is proud to lead high-performance design-build teams along the East Coast for:

      • WSSC Water: Utilizing thermal hydrolysis process to transform regional biosolids management, generate biogas and reduce operating costs. Learn More
      • City of Bunnell, Florida: Providing clean drinking water using Reverse Osmosis technology.
      • Clayton County Water Authority: Increasing treatment capacity and incorporating advanced treatment processes for emerging contaminant removal.
      • Charlotte Water: Efficient biosolids treatment incorporating thermal hydrolysis process.
      • Arlington County, Virginia: Reducing greenhouse gas emissions and advancing sustainability goals using thermal hydrolysis process. Learn More
      • City of New Smyrna Beach, Florida: Incorporating cutting edge water softening and purification technologies.
      • City of Atlanta, Georgia: Providing critical pumping system improvements to secure Atlanta鈥檚 water supply for the next 100 years. Learn More

Want to learn more? A team of PC design-build leaders from across our regions are eager to connect with our industry partners at the DBIA Water/Wastewater Conference. Stop by booth #517 to say hello, check out our new look, and enjoy a mouthwatering giveaway!

The post Join PC Construction at the DBIA Water/Wastewater Conference appeared first on PC Construction.

]]>
Major Operational Milestone for WSSC鈥檚 Piscataway WRRF Bioenergy Project /news/major-operational-milestone-for-wsscs-piscataway-wrrf-bioenergy-project/ Wed, 05 Jun 2024 19:18:22 +0000 /?p=11837 Last night brought a lot of excitement to the $271 million Piscataway WRRF Bioenergy Project, which centers on the addition of the thermal hydrolysis and anaerobic digestion processes to produce Class A biosolids. In the words of our friends at WSSC Water, 鈥淟ast night, a bundle of innovation was born.鈥?This quip refers to the […]

The post Major Operational Milestone for WSSC鈥檚 Piscataway WRRF Bioenergy Project appeared first on PC Construction.

]]>
WSSC Piscataway WRRF Bioenergy Project Seeding THPLast night brought a lot of excitement to the $271 million Piscataway WRRF Bioenergy Project, which centers on the addition of the thermal hydrolysis and anaerobic digestion processes to produce Class A biosolids. In the words of our friends at WSSC Water, 鈥淟ast night, a bundle of innovation was born.鈥?/p>

This quip refers to the next phase of operational start-up requiring initial seeding of the anaerobic digester. The anaerobic digestion process harnesses natural bacteria to treat wastewater biosolids. At WSSC, these biosolids will first flow through the new thermal hydrolysis process (THP) followed by the anaerobic digesters (ADs). When initially commissioned, anaerobic digestion facilities require seeding with biologically active sludge to produce the population of methanogenic and acid-forming bacteria required for the anaerobic digestion process to work effectively. To accelerate the process of acclimation of the bacteria to the new environment, the preference is to seed with biologically active sludge that has gone through similar processes, in this case THP.

DC Water, located less than 15 miles from the WSSC Piscataway WRRF, also incorporated THP and anaerobic digestion at their Blue Plains AWWTP facility with the Main Process Train project, which was completed by PC in 2015. As a fully established facility, DC Water was happy to provide 鈥渂ugs鈥?that are 鈥渢rained鈥?to jump start the anaerobic digestion process. Beginning last night, tanker trucks containing this biologically active sludge began rolling into WSSC鈥檚 bioenergy facility and this sharing of special resources will continue over the next five days. Click here to watch last night鈥檚 excitement.

Once the seeding process is complete, initiation of full-time operation of the THP processes will begin. In preparation for this, the WSSC operations team has concurrently begun pre-dewatering activities, processing the indigenous biosolids produced by the Piscataway WRRF and storing the dewatered cake in the new cake storage silos. The volume of biosolids processed will ramp up from 4 dry tons per day to 16 dry tons per day over a 30-day period. Once this is complete, the facility will operate for another 60 days solely processing Piscataway WRRF biosolids before bringing biosolids from WSSC鈥檚 four other facilities to the site for processing through the new systems.

The Piscataway WRRF Bioenergy Project utilizes cutting-edge green technology to transform the way WSSC handles biosolids from all six of their water resource recovery facilities, significantly reducing the volume and creating Class A biosolids. The process will also reduce operating costs by more than $3 million per year and reduce greenhouse gas emissions by 15% by capturing and cleaning the digester gas to help power the facility through the CHP facility.

WSSC Piscataway WRRF Bioenergy Project Site Overview

The post Major Operational Milestone for WSSC鈥檚 Piscataway WRRF Bioenergy Project appeared first on PC Construction.

]]>
The Cambi THP System Arrives at WSSC Piscataway Bio-Energy Project /news/the-cambi-thp-system-arrives-at-wssc-piscataway-bio-energy-project/ Tue, 24 Aug 2021 19:59:54 +0000 https://www.pcconstruction.com/blog/?p=6646 The excitement on site was visible when the first truck delivering the Cambi unit arrived at the Piscataway site. Over the course of three days, nine trucks arrived delivering the modular Cambi components for installation by the PC team. This was not PC鈥檚 first Cambi installation. The onsite team had the experience and lessons learned […]

The post The Cambi THP System Arrives at WSSC Piscataway Bio-Energy Project appeared first on PC Construction.

]]>

The excitement on site was visible when the first truck delivering the Cambi unit arrived at the Piscataway site. Over the course of three days, nine trucks arrived delivering the modular Cambi components for installation by the PC team.

This was not PC鈥檚 first Cambi installation. The onsite team had the experience and lessons learned from installing the largest Cambi system in the world at DC Water鈥檚 Blue Plains AWWTP. The benefits of the planning process was evident as the trucks arrived in a set sequence and the modular equipment was offloaded directly to the awaiting concrete pad. Always with an eye on safety, PC鈥檚 team first erected the four smaller reactor tanks, followed by the feed pump skid, the flash tank and pulper tank and finally the walkway platforms and piping connecting the system.

This fall, a secondary pulper and feed tank will be delivered and installed. These components will ensure continuous operation during maintenance and inspection periods and will be the first Cambi system in the world with this additional operational capacity.

While the delivery and installation of Cambi was a key milestone, several other components have continued to progress. Dutchland has made significant progress on the deammonification tanks. After pouring the three base slabs, each sitting on a different elevation, they began erecting the 89 wall panels that form the tank as well as the 30 additional beam, walkway, roof and floor panels. With everything erected, large steel tendons were pulled through the panels and tensioned to achieve structural integrity and watertightness. The tanks are now ready for testing.

The PC team has also completed the cake storage pad facility, which will house the final Class A biosolids before it is hauled offsite. Work continues on the foundation for the cake receiving facility where trucks from other WSSC sites will deliver sludge to be processed through the THP facility.

DN Tanks is nearing completion on the two 1.5-million-gallon digester tanks. Foundations for the CHP, gas cleaning and storage facilities are being prepped and poured in anticipation of the equipment delivery.

Looking forward, Nitterhouse will soon be back on site erecting the precast concrete wall and roof system for the Solids building.

Stay tuned for updates as the Piscataway landscape continues to change!

Check out the progress:

The post The Cambi THP System Arrives at WSSC Piscataway Bio-Energy Project appeared first on PC Construction.

]]>
Alan Parent Earns National Design-Build Certification /news/alan-parent-earns-national-design-build-certification/ Tue, 01 Jun 2021 12:53:36 +0000 https://www.pcconstruction.com/blog/?p=6610 PC is pleased to announce that Alan Parent, the director of business development for PC鈥檚 water and wastewater construction market, has successfully completed the Design-Build Institute of America鈥檚 comprehensive education and certification testing program. Alan has over 20 years of substantial design-build project delivery experience and has achieved the design-build industry鈥檚 highest designation as a […]

The post Alan Parent Earns National Design-Build Certification appeared first on PC Construction.

]]>
PC is pleased to announce that Alan Parent, the director of business development for PC鈥檚 water and wastewater construction market, has successfully completed the Design-Build Institute of America鈥檚 comprehensive education and certification testing program. Alan has over 20 years of substantial design-build project delivery experience and has achieved the design-build industry鈥檚 highest designation as a nationally certified Design-Build Professional庐.

Some of Alan鈥檚 previous work with design-build projects includes the Main Process Train and Wet Weather Facility projects at the Blue Plains AWWTP project in DC, the Ralph Brennan WTP Gravity Filters Upgrades in Florida, the Hopewell Regional WWTF Phase 2 project in Virginia, and currently, the WSSC Piscataway Bio-Energy Project in Maryland.

Alan joins a growing industry of design-build professionals who are redefining project delivery throughout the United States. His commitment to the progress of the design-build methodology will help guide PC鈥檚 efforts as a leader in design-build construction.

The post Alan Parent Earns National Design-Build Certification appeared first on PC Construction.

]]>
Big Changes at WSSC Piscataway Bio-Energy Project /news/big-changes-at-wssc-piscataway-bio-energy-project/ Fri, 14 May 2021 17:06:22 +0000 https://www.pcconstruction.com/blog/?p=6603 May is bringing some very visible changes to the landscape of the WSSC Piscataway Water Resource Recovery Facility. The $271 million Bio-Energy Project has been under construction for nearly a year and, with the initial site work complete, several of the project鈥檚 structures have started to take shape. Most recently, we鈥檝e had 11 different subcontractors […]

The post Big Changes at WSSC Piscataway Bio-Energy Project appeared first on PC Construction.

]]>
May is bringing some very visible changes to the landscape of the WSSC Piscataway Water Resource Recovery Facility. The $271 million Bio-Energy Project has been under construction for nearly a year and, with the initial site work complete, several of the project鈥檚 structures have started to take shape. Most recently, we鈥檝e had 11 different subcontractors onsite.

PC鈥檚 self-perform team has set the seven belt filter presses at what will be the solids building housing all the pre- and post-dewatering activity for the facility. These are just a few of the large pieces of equipment being set into place prior to erecting the pre-cast concrete panels that will form this more than 16,000-square-foot building.

Nitterhouse Concrete has started to place the precast panels on several buildings including the chemical storage building, sidestream pump station and gas storage blower building. They will also begin erecting the solids building once PC completes the equipment installation.

Work continues on the two 1.5-million-gallon anaerobic digesters, including the massive cast-in-place concrete domes. Work is being completed on the structural integrity of the tanks and making them watertight through the process of wrapping and shotcreting the tanks.

The sidestream treatment tanks are starting to take shape as well. Dutchland鈥檚 team is onsite placing the foundations for the pre-cast post-tensioned tanks that will be erected in June.

Additionally, the cake receiving vault has been completed in preparation for the cake hoppers and cake storage bins. Foundations are being prepped for the generators, boilers and gas storage facility.

While so much has happened in the past month, the flurry of activity won鈥檛 end anytime soon. Stay tuned for more updates coming soon!

The post Big Changes at WSSC Piscataway Bio-Energy Project appeared first on PC Construction.

]]>
Stonehenge Recreated at WSSC鈥檚 Piscataway WRRF /news/stonehenge-recreated-at-wsscs-piscataway-wrrf/ Mon, 21 Dec 2020 21:13:54 +0000 https://www.pcconstruction.com/blog/?p=6369 One of the key components of WSSC鈥檚 new bio-energy project is the construction of two 1.5-million-gallon anaerobic digesters. As two of the earliest structures to be built on the project, there was a lot of excitement over the past few days as the tanks have started to take shape. PC has partnered with DN Tanks […]

The post Stonehenge Recreated at WSSC鈥檚 Piscataway WRRF appeared first on PC Construction.

]]>
One of the key components of WSSC鈥檚 new bio-energy project is the construction of two 1.5-million-gallon anaerobic digesters. As two of the earliest structures to be built on the project, there was a lot of excitement over the past few days as the tanks have started to take shape.

PC has partnered with DN Tanks to complete these circular prestressed concrete tanks. Each tank consists of 17 individual panels that are 50 feet tall and vary in width to create an approximately 78-foot-diameter tank. The largest panel weighed in at more than 30 tons.

The panels were cast on site in eight casting beds, four near each tank location. Once the casting was complete, each bed contained four or five stacked panels. Using a 500-ton crane, the panels were lifted from their beds and flown into place. Each tank took only two days to complete.

Now that the panels are in place, work can begin on the installation of the shoring and formwork to cast the digester domes. The tank joints still need to be infilled and the tanks wrapped with prestressing wire and coated with shotcrete. The tanks are expected to be fully constructed in Spring 2021.

The $271 million bio-energy project will use thermal hydrolysis process (THP) and anaerobic digestion to treat the biosolids and a sidestream process to treat the resulting effluent. The project is also designed to capture and clean the digester gas to feed back to the Washington Gas pipeline and/or to be used in the new CHP facility to generate electricity and steam to feed the THP process. The entire project is expected to be complete by the fall of 2024.

The post Stonehenge Recreated at WSSC鈥檚 Piscataway WRRF appeared first on PC Construction.

]]>
Focus Shifts from Site Preparation to Construction at the WSSC Bio-Energy Project /news/focus-shifts-from-site-preparation-to-construction-at-the-wssc-bio-energy-project/ Wed, 23 Sep 2020 14:37:21 +0000 https://www.pcconstruction.com/blog/?p=6340 Activity on the Early Works Package at WSSC鈥檚 Piscataway WRRF site began almost a year ago and now nears completion as the teams shift focus to Phase 2 construction activities associated with the new bio-energy facility. Since last September, the team has completed demolition, the upgrade and relocation of site utilities and site preparations for […]

The post Focus Shifts from Site Preparation to Construction at the WSSC Bio-Energy Project appeared first on PC Construction.

]]>
Activity on the Early Works Package at WSSC鈥檚 Piscataway WRRF site began almost a year ago and now nears completion as the teams shift focus to Phase 2 construction activities associated with the new bio-energy facility. Since last September, the team has completed demolition, the upgrade and relocation of site utilities and site preparations for construction.

WSSC gave PC Construction the Notice to Proceed on Phase 2 construction in June. Since then, early subcontractors have mobilized and work is underway with a focus on the early foundation work over the summer. To date, this work includes:

  • More than 100 auger cast piles have been installed to support the two new 1.5 million-gallon anaerobic digesters and digester control building.
  • Additional erosion controls have been put in place.
  • Base slab concrete for the filtrate pump station and the sidestream chemical storage building are underway.
  • Construction has begun on a warehouse for materials storage.
  • Subgrade preparation for the cake storage facility was completed.
  • Support of excavation installation has commenced for the construction of the cake receiving vault.

The site is now bustling with activity as we move forward with this exciting project. Stay tuned for more updates!

The post Focus Shifts from Site Preparation to Construction at the WSSC Bio-Energy Project appeared first on PC Construction.

]]>
Phase 2 Begins for WSSC鈥檚 Innovative Bio-Energy Project /news/wsscbioenergybegins/ Tue, 09 Jun 2020 13:27:53 +0000 https://www.pcconstruction.com/blog/?p=6251 In April, the WSSC Water Commissioners approved Phase 2 funding, allowing PC to begin construction of the design-build Piscataway WRRF Bio-Energy Project in Accokeek, Maryland. The $228 million for Phase 2 brings the total investment in the green-energy project to $270 million and marks the final funding needed to construct WSSC Water鈥檚 largest and most […]

The post Phase 2 Begins for WSSC鈥檚 Innovative Bio-Energy Project appeared first on PC Construction.

]]>

In April, the WSSC Water Commissioners approved Phase 2 funding, allowing PC to begin construction of the design-build Piscataway WRRF Bio-Energy Project in Accokeek, Maryland. The $228 million for Phase 2 brings the total investment in the green-energy project to $270 million and marks the final funding needed to construct WSSC Water鈥檚 largest and most technologically advanced project. At the heart of the project is how WSSC Water handles biosolids produced by the wastewater treatment process.

This new bio-energy facility will use thermal hydrolysis process (THP) and anaerobic digestion to treat the biosolids and a sidestream process to treat the nutrient rich effluent from the dewatering process. The project is also designed to capture and clean the digester gas to feed back to the Washington Gas pipeline and/or to be used in the new CHP facility to generate electricity and steam to feed the THP process. Surplus electricity generated can also be fed back to the electrical grid.

The facility has been designed to meet WSSC Water鈥檚 anticipated 2040 capacity with the THP鈥檚 capacity of 88 dry tons per day. The two digesters have a combined volume/capacity of more than 3 million gallons.

In addition to the major process facilities, the project also includes gravity thickening, a cake receiving facility that will accept solids from WSSC Water鈥檚 other WRRF鈥檚, pre- and post-dewatering facilities, digested sludge storage, odor control facilities, a post-dewatering cake storage facility, and a gas storage and cleaning facilities.

Using cutting-edge 鈥済reen鈥?technology, the new facility will significantly reduce the amount of biosolids resulting from the treatment process, thus reducing costs to haul and dispose of the product. The remaining biosolids will be significantly cleaner (Class A), making the disposal process much easier and allowing the final product to be suitable for sale and distribution as fertilizer. This new process will reduce operating costs and is anticipated to save WSSC Water customers more than $3 million per year. Additionally, by recovering the digester gas and using it to help run the facility, WSSC Water will reduce their greenhouse gas emissions by 15 percent.

PC is underway with Phase 2 work as we continue toward completion of Phase 1 early work activities, referred to as the enabling work package, which includes demolition of existing facilities, hazardous materials abatement, site preparation and site utilities enhancements. This Phase 1 work is about 75% complete with most major demolition nearing completion. All work associated with the Phase 1 site preparation is scheduled to be complete in late August 2020.

To complete this project, PC is teaming with leaders in these specialized facilities 鈥?Stantec and Hazen and Sawyer. This winning combination brings together PC鈥檚 construction experience 鈥?including the largest THP facility in the world 鈥?with Stantec鈥檚 history of designing nearly half of the world鈥檚 THP facilities and Hazen and Sawyer鈥檚 biosolids and sidestream treatment expertise.

We are excited to collaborate with WSSC to move this environmentally significant project to successful completion. Stay tuned for more updates as this project progresses.

Photos: A look at the Piscataway WRRF site prior to construction (top) and currently (bottom).

The post Phase 2 Begins for WSSC鈥檚 Innovative Bio-Energy Project appeared first on PC Construction.

]]>
Work Underway for WSSC鈥檚 Bio-Energy Project /news/work-underway-for-wsscs-bio-energy-project/ Mon, 02 Dec 2019 20:15:31 +0000 https://www.pcconstruction.com/blog/?p=6218 PC received the Notice to Proceed for the WSSC Bio-Energy Project Early Work Package earlier this fall. As part of this work, the team is in the process of removing hazardous materials from several buildings, installing erosion control measures, cleaning digesters and underground piping, clearing the adjacent ballfield that will house the trailer complex and […]

The post Work Underway for WSSC鈥檚 Bio-Energy Project appeared first on PC Construction.

]]>

PC received the Notice to Proceed for the WSSC Bio-Energy Project Early Work Package earlier this fall. As part of this work, the team is in the process of removing hazardous materials from several buildings, installing erosion control measures, cleaning digesters and underground piping, clearing the adjacent ballfield that will house the trailer complex and beginning work on a temporary access road to the trailer complex.

December will bring demolition of the incinerator building to make room for the new bio-energy facility, demolition of ductbanks around the site and the installation of the construction trailer complex.

Work will continue through July 2020 with additional demolition, plant drain improvements and utility relocation. All this work is setting the stage for construction of the bio-energy facility, which is anticipated to begin in Spring 2020.

Click here for more information about this project.

The post Work Underway for WSSC鈥檚 Bio-Energy Project appeared first on PC Construction.

]]>
Project Update: Blue Plains AWWTP TDPS/ECF Passes Operational Demonstration /news/project-update-blue-plains-awwtp-tdps-ecf-passes-operational-demonstration/ Wed, 21 Feb 2018 15:30:16 +0000 https://www.pcconstruction.com/blog/?p=5796 Starting-up equipment and moving millions of gallons of water at 3 a.m. has become the norm on the Tunnel Dewatering Pump Station and Enhanced Clarification Facility (TDPS/ECF) project as the team has worked toward, and now successfully completed, the system operational demonstration. This was the final full-system acceptance test before the tunnel bulkheads are removed […]

The post Project Update: Blue Plains AWWTP TDPS/ECF Passes Operational Demonstration appeared first on PC Construction.

]]>
ACTIFLO rapid rate clarifiers during operational testing.

Starting-up equipment and moving millions of gallons of water at 3 a.m. has become the norm on the Tunnel Dewatering Pump Station and Enhanced Clarification Facility (TDPS/ECF) project as the team has worked toward, and now successfully completed, the system operational demonstration. This was the final full-system acceptance test before the tunnel bulkheads are removed from the influent tunnels, allowing combined sewer overflows (CSOs) during storms to be sent to the facility.

The facility is designed to treat 225 million gallons of incoming CSO from tunnels underneath Washington, D.C. Water enters through a 23-foot diameter tunnel and is stored in a shaft before being pumped by 83-mgd pumps to the ECF.

For the operational demonstration, influent was pumped from the existing plant to the ECF for treatment. The fine screens removed all solids larger than 6 millimeters from the influent and sent the material to storage containers for removal. The influent was then injected with ferric chloride and caustic soda to aid in settling and neutralize the pH before entering the grit vortexes. The influent then entered the three ACTIFLO High Rate Clarification trains, which are the largest in the world, and include coagulation, flocculation and settling tanks. The removal rates that were achieved far exceed the contract required performance guarantee.

Now that this test is complete, contractors upstream of the system can remove their bulkheads that are currently blocking flow from entering the facility. While that is taking place, our team will continue to make minor adjustments to the system, pump at limited capacity to keep the tunnel dry, and prepare for our next phase of testing scheduled to begin in early March. This next phase of testing will prove the facilities鈥?ability to handle the large combined sewer overflows the plant was designed to treat.

The post Project Update: Blue Plains AWWTP TDPS/ECF Passes Operational Demonstration appeared first on PC Construction.

]]>
Wildcat Stadium Receives DBIA Recognition /news/wildcat-stadium-receives-dbia-recognition/ Wed, 14 Feb 2018 15:00:46 +0000 https://www.pcconstruction.com/blog/?p=5786 PC Construction was recently recognized by the New England chapter of the Design-Build Institute of America with a 2017 Design-Build Award Honorable Mention for the University of New Hampshire Wildcat Stadium project. While the award has PC Construction鈥檚 name on it, the success of this project is really a result of so many people and […]

The post Wildcat Stadium Receives DBIA Recognition appeared first on PC Construction.

]]>
Football Field and StadiumPC Construction was recently recognized by the New England chapter of the Design-Build Institute of America with a 2017 Design-Build Award Honorable Mention for the University of New Hampshire Wildcat Stadium project. While the award has PC Construction鈥檚 name on it, the success of this project is really a result of so many people and firms coming together to achieve a common goal.

When the University of New Hampshire was ready to move forward with the construction of their state-of-the-art NCAA Division I stadium, they turned to design-build delivery to ensure all their project goals were met. Teaming with PC Construction, Lavallee Brensinger Architects and Populous, design commenced immediately with construction following in May 2015. An aggressive schedule was adopted to meet the university鈥檚 required late summer 2016 completion date to accommodate the football season鈥檚 opening game. The design-build delivery method, combined with the release of early work packages and innovative problem-solving, allowed the team to deliver on time.

There are so many reasons why this project was a success. Certainly, having the right team involved from the start was a critical factor. The team embraced a highly collaborative environment, working together to achieve UNH鈥檚 vision. In addition, having early involvement by PC Construction enhanced the design and constructability review process and allowed the team to discover conflicts between proposed design and actual constructible conditions. Time and money was saved through this collaboration and cemented the team鈥檚 synergy throughout the project.

And, of course, the top-notch design epitomized the grandeur UNH sought out to achieve for their Wildcat Athletics program. Take in one game at Wildcat Stadium and you鈥檒l know exactly what we mean.

So, thank you to everyone who contributed to this incredible project. We are truly honored to have been your partner.

The post Wildcat Stadium Receives DBIA Recognition appeared first on PC Construction.

]]>